Commercial fit out: what does the electrical contractor need from you?
An electrical contractor on a commercial fit out needs four things before day one: the landlord’s licence to alter, a survey of what the CAT A shell already provides, a decided layout with every piece of tenant kit on it, and a programme with the isolations and out of hours work agreed. Settle those and the electrical package runs to programme.
- CAT A is the landlord’s shell. CAT B is the tenant’s fit out, and that is where most of the electrical work sits.
- The lease almost always needs a licence to alter before anyone drills a hole. Get it moving first.
- The shell survey decides the design: supply capacity, the landlord’s board, metering and what CAT A really left.
- Fire alarm and emergency lighting are fire safety systems. They are not ours, and they should not be quietly included in an electrical package.
- The handover pack is part of the job, not a favour. The landlord will want a copy of it.
What is the difference between a CAT A and a CAT B fit out, electrically?
CAT A is what the landlord provides to make the floor lettable. CAT B is what the tenant adds to make it theirs, and that is where most of the electrical work on a fit out sits.
A typical CAT A shell has an incoming supply and a landlord’s board, basic lighting to an open floor, and the base fire alarm and emergency lighting. Nothing on it is where the tenant will want it.
CAT B is partitions, meeting rooms, a tea point, the desk layout, the comms room, and the lighting that follows the new rooms. Every one of those has a cable in it, so the electrical package is mostly CAT B, designed round a shell somebody else built.
Do we need the landlord’s permission before the electrician starts?
Almost always, yes. A commercial lease normally forbids alterations without the landlord’s written consent, and the document that gives it is a licence to alter.
The law says a landlord cannot unreasonably withhold consent to improvements, but it does not say they have to be quick, and the licence is where the conditions live: cable and containment types, where you may not fix, drawings reviewed by the landlord’s consultant, copies of every certificate, and what must be reinstated at lease end.
Start the licence the day the design is agreed. Send us the draft with the drawings and we will price to its conditions rather than discover them in week two.
What does the electrician check in the shell before pricing?
The supply, the board, the metering and the condition of what is already there. A quote written without seeing them is a guess.
- Supply capacity. What the landlord has allocated to the demise, single or three phase, and whether it will carry the kit. Our three phase article covers it.
- The landlord’s board. Spare ways, protective devices, where the tenant’s submain lands, and whether a new board for the demise is the cleaner answer.
- Metering. Whether the demise is separately metered. Sub-metering is often a licence condition and it goes in at first fix, not afterwards.
- The existing installation. A condition report on what CAT A left says whether the lighting and containment can be reused. Reuse is cheaper only if it tests clean.
- The routes. Floor depth, ceiling void, risers, and what already occupies them.
As an occupier you take on a standing duty under the Electricity at Work Regulations for the system in your premises the day you move in, so what the shell contains is your problem too.
What does the electrician need to know about the tenant’s kit?
Everything with a plug or a cable, before first fix, on a drawing. The layout is the gate on a fit out just as it is on a house build, and the list is longer than people expect.
Desks and how they get power: floor boxes, power poles or perimeter trunking, with data or without. The tea point or kitchen. The comms room and its cooling. Air conditioning, which is normally the mechanical contractor’s kit on our supply, so the loads are agreed between the two trades. Signage, EPOS, access control, CCTV, screens, EV charge points outside.
Lighting gets decided last and should be decided first. Under Part L of the Building Regulations, new lighting in a non-domestic building has to meet efficacy and control requirements, which in practice means LED with occupancy or daylight control in most rooms. The layout follows the partitions, so it cannot be fixed until the room plan is.
How does the electrical work fit the fit out programme?
First fix goes in once partitions are framed and before they are boarded, second fix after decoration, and testing sits on the programme as its own item. That much is the same as any build, and our first and second fix article covers it.
What is different on a fit out is the building around you. The floor below is trading, the riser is shared, and the isolation you need to connect the submain takes the neighbouring tenant off too. Isolations are agreed with the managing agent in advance, usually out of hours, and a programme that has not allowed for that has a gap in it. Live premises are normal for us.
CDM 2015 applies to fit outs like any other construction work. The principal contractor plans and coordinates, and every contractor, including us, has duties to plan and manage its own work. RAMS come as standard.
Who does the fire alarm and emergency lighting on a fit out?
A fire specialist, not us, and we say so at the start rather than including it and hoping.
A fit out changes escape routes. New partitions, rooms and doors mean the emergency lighting and detection designed for the open CAT A floor no longer match the building, and the responsible person under the Fire Safety Order has to have a system that suits the premises as they now are. That is a design question answered against the fire strategy, then installed, commissioned and certified by people who do that work all day.
Here is the honest bit. Plenty of electrical contractors put a line for emergency lighting in a fit out package because it wins the job. What the tenant gets is fittings on a circuit with no design behind them and a certificate that does not say what the fire officer or the insurer will ask for. We install the containment and supplies the fire contractor needs and leave the design and certification to them. If that costs us the odd package, so be it.
What should the handover pack contain, and does building control need to know?
An Electrical Installation Certificate for the new work, with the test results and a board schedule that matches the labels. As-installed drawings, because the design drawing never survives the ceiling void. Commissioning records for the lighting controls. An operation and maintenance pack where the contract asks for one. And the copies the licence says the landlord gets.
Building control is separate. Electrical work in a commercial building is not notifiable under Part P, which only covers dwellings, but the fit out as a whole may need building regulations approval for the partitions, fire precautions, ventilation and Part L lighting, and the electrical certificate is part of the evidence at completion. The fit out contractor usually holds that application. Our paperwork is ready when it is asked for.
What changes the price of a fit out electrical package?
We price from drawings, the licence and the shell survey, not a rate per square foot.
- The point count and the desk power method: floor boxes and power poles are different jobs.
- Whether the landlord’s board and supply can take the load, or a new board and submain are needed.
- How much of the CAT A lighting and containment can honestly be reused.
- The licence conditions: specified cable types, restricted fixing, reinstatement at lease end.
- Out of hours working and the number of isolations the building needs.
- The kit: a kitchen, a comms room, air conditioning, EV charging.
Send the drawings, the draft licence and your programme through our quote page, or see how we run commercial fit outs first. We will tell you what the shell can take before we tell you a number.
Questions we get asked about this
How long does an office fit out take?
It depends on the floor and how much CAT B work there is. What stretches the electrical package is the licence to alter, the landlord’s isolations and kit that is not on site, not the wiring.
Do I need a licence to alter for electrical work?
Almost always. Most commercial leases forbid alterations without the landlord’s written consent, and new circuits, containment and lighting changes are alterations. Check the lease and start the licence as soon as the drawings exist.
Is an EICR needed before a fit out?
It is not a legal precondition, but a condition report on the shell is the only way to know what the landlord has really left you and whether any of it can be reused. Many leases and insurers ask for one anyway, and it is far cheaper before the ceilings go in.
Does a commercial fit out need building regulations approval?
Often, for the partitions, fire precautions, ventilation and lighting, though not because of the electrics on their own: Part P notification only applies to dwellings. The fit out contractor usually holds the application and the electrical certificate forms part of the completion evidence.
- Landlord and Tenant Act 1927, section 19, consent to alterations, legislation.gov.uk
- The Electricity at Work Regulations 1989, legislation.gov.uk
- The Construction (Design and Management) Regulations 2015, legislation.gov.uk
- CDM 2015, who does what on a construction project, hse.gov.uk
- The Regulatory Reform (Fire Safety) Order 2005, legislation.gov.uk
- Fire safety in the workplace, your responsibilities, gov.uk
- Approved Document L, conservation of fuel and power, gov.uk
- Building regulations approval, when you need it and how it works, gov.uk
- BS 7671, the IET Wiring Regulations, electrical.theiet.org
Checked on 13 October 2026. Regulations change, so if you are reading this a long way after that date, ring us and we will tell you what has moved.
Read this next
First and second fix: when does the electrician need to be on site?
The two windows an electrician needs in your programme, who certifies the work, and what really makes a date slip.
Three phaseDo I actually need a three phase supply?
Why most homes and small units do not need one, and what to fix instead when the power runs out.
Solar and batterySolar and battery for business premises: what does the install involve?
Half hourly data, the G99 application, the roof check and the paperwork, and when a battery does not pay.