HomeAdviceWhy do the lights dim when a big machine starts?
Three phase

Why do the lights dim when a big machine starts?

The lights dim because a motor draws several times its running current for the moment it starts, and that surge pulls the voltage down across every cable, board and joint between the supply and the machine. Lighting on the same route shows the dip. The fix is usually in your own wiring, not a bigger supply.

Written by Brady Lewis, qualified electrician ·06 October 2026 ·5 min read ·NICEIC Approved Contractor
The short version
  • A brief dip when a large motor starts is physics. A deep or lasting one is a fault in the design or the installation.
  • The dip happens wherever there is resistance: the machine circuit, a shared submain, a tired joint, or the incoming supply.
  • Measuring the voltage at each point while the machine starts tells you which one it is.
  • Most fixes are inside the building: a properly sized submain, lighting moved off the machine’s route, or a soft starter.
  • A bigger or three phase supply feeding the same undersized cable changes nothing.

Why does a machine starting make the lights dim?

Because a motor is greedy for the first second or two. Before it is spinning it draws several times the current it uses once it is running, and current flowing through any resistance loses voltage on the way.

Every cable, every terminal and the supply itself has a little resistance. At normal load the loss is small and nobody notices. When a compressor, a saw, a lift or a large extractor starts, the surge multiplies that loss for a moment, and everything sharing the same route sees a lower voltage. Lights are where you notice it, because your eye picks up a flicker that a socket circuit never shows.

A short, shallow dip on a big motor start is normal. Lights that dip hard, stay dim, or dip when something small starts are telling you the route has more resistance than it should.

Where does the voltage get lost?

In one or more of four places, and the cure for each is different.

  • The machine’s own circuit. A long run on a cable chosen for the running current, not the starting current, loses too much voltage at start.
  • A shared submain. The commonest cause in a workshop or unit. The board the machine is on is fed by a cable sized years ago for less load, and the lighting is fed from the same board.
  • A poor connection. A loose or corroded terminal behaves like a resistor. It also gets hot. Dimming together with a warm smell, discoloured accessories or a buzzing board is not a nuisance, it is a fault to get looked at this week.
  • The incoming supply. Sometimes the dip is already there at the cut out, because the building is at the end of a long network cable or shares a transformer with heavy users.

BS 7671 sets voltage drop limits for an installation in normal use, a smaller allowance for lighting than for other circuits, and a good design checks the start condition of big motors too. An installation that has grown one machine at a time has usually never had that check.

How does an electrician find the cause?

By measuring, not guessing. We put a recorder on the supply at the cut out, at the board the machine is on and, where we can, at the machine itself, then start the machine and watch what the voltage does at each point.

If the dip is small at the cut out and large at the board, the submain is the problem. If it is small at the board and large at the machine, it is the machine circuit. If it is already outside the limits at the cut out, it is the network.

Alongside that we check the loop impedance of the circuits involved, look at what is actually connected against what each cable was sized for, and go over the terminations, often with a thermal camera while the load is on. A loose joint shows up as a hot spot before it shows up as anything worse. As the person in control of the premises you have a duty under the Electricity at Work Regulations to keep the system safe, and this is part of that.

Do we need a bigger supply, or three phase?

Rarely, and this is where a lot of money gets wasted. A new or upgraded supply makes more capacity available at the cut out. If the voltage is being lost inside the building, on a submain or a joint, a bigger supply feeds the same bottleneck and the lights dim exactly as before.

Three phase is the right answer when the real maximum demand is more than the supply can carry, or when a machine needs 400 volts. Our three phase article covers that decision. A dimming light is not on its own a reason to apply.

The exception is when the measurements show the voltage at your cut out falling outside the legal range. The supply is declared at 230 volts and must stay within 10 per cent above and 6 per cent below it. If it does not, that is the network operator’s to investigate, and we give you the recordings to send them.

What actually fixes it?

It depends on where the voltage is lost, which is why the measuring comes first.

  • A new or larger submain to the board the machines are on, sized for the start condition rather than the running load.
  • Separating the lighting onto its own board or a different route, so a motor start does not travel through the lights.
  • Remaking poor connections and replacing damaged accessories found in the inspection.
  • A soft starter or an inverter drive on the machine, which ramps it up instead of starting it in one hit. This is usually agreed with the machine supplier, because it affects how the machine runs.
  • Rebalancing the load across the phases on a three phase board, where one phase is doing most of the work.

Often it is two of these together. The answer is in the readings, and we would rather show you them than sell you the biggest item on the list.

What changes the price?

We price from what the investigation finds, so the first job is the investigation itself.

  • How many boards and machines need recording, and whether we can do it during normal working.
  • The length and route of any new submain: through an occupied unit, along existing containment, or new.
  • Whether the board the machines are on needs replacing or just a better feed.
  • Out of hours working for the isolations.
  • Any repairs the inspection finds along the way.

Tell us what dims, what starts and how long it has been happening through our quote page, or read how we handle commercial three phase and machine supplies.

Questions we get asked about this

Why do my lights dim when my compressor starts?

The compressor motor draws a surge of current as it starts, and that surge pulls the voltage down on every cable it shares with the lights. A brief flicker is normal; a deep or lasting dip means too much resistance somewhere on the route.

Is it normal for lights to dim when a motor starts?

A short, shallow dip on a large motor is normal. Dimming that is deep, lasts, gets worse over time or happens with small loads is not, and it should be measured.

Can voltage drop damage equipment?

It can. Motors that start on a low voltage run hotter and take longer to get going, contactors can drop out, and electronic equipment can reset. A loose connection causing the drop is also a fire risk in its own right.

Will a soft starter stop the lights dimming?

Often it reduces the dip a lot, because it limits the starting surge. It does not fix an undersized submain or a bad joint, so measure first and fit one when the readings say the start itself is the problem.

Sources
  1. The Electricity Safety, Quality and Continuity Regulations 2002, regulation 27, legislation.gov.uk
  2. Find my network operator, energynetworks.org
  3. The Electricity at Work Regulations 1989, legislation.gov.uk
  4. Electrical safety at work, hse.gov.uk
  5. BS 7671, the IET Wiring Regulations, electrical.theiet.org

Checked on 13 October 2026. Regulations change, so if you are reading this a long way after that date, ring us and we will tell you what has moved.

Brady Lewis

Qualified electrician and director, Excel Electrical Installations Ltd

Brady runs Excel Electrical from Olney and has worked in the trade for over ten years, across domestic, commercial and social housing. He holds 18th Edition and inspection and testing qualifications, and the company is an NICEIC Approved Contractor.

Read this next

Rather have someone look at it than read about it?

Ring 01908 464338, send a photo on WhatsApp, or get a free quote online. Most quotes go back the same working day.

Call Free quote